INFORMATION ON GAS RATES AND CHARGES
STANDARD CONTINUING TARIFF
The Standard Continuing Tariff is applicable to all gas consumption in the following instances:
- As an interim tariff that will come into effect if, after your current Gas Supply Agreement with AGL | Perth Energy has passed its “Contract End Date”, and you continue to use gas without entering into a new Gas Supply Agreement with AGL | Perth Energy; and/or
- Where you are being supplied gas pursuant to AGL | Perth Energy’s Gas Standard Form Contract, this is price referred to as the “Contract Price”, and this paragraph forms the price element of the “Customer Schedule” referred to in that contract.
As at 1 August 2024, the Standard Continuing Tariff is as follows:
Prices exclude GST | Gas Prices (Unbundled) |
Gas Prices (Bundled) |
Gas Prices (Unbundled) |
Gas Prices (Bundled) |
---|---|---|---|---|
Until 31st August 2024 | From 1st September 2024 | |||
Consumption Tariff (per Gigajoule) | $20/GJ | $27.60/GJ | $20/GJ | $27.60/GJ |
Daily Supply Charge | $1.99 meter/day | $1.99 meter/day | $4.98 meter/day | $4.98 meter/day |
Please note that the Standard Continuing Tariff is subject to change periodically as published by AGL | Perth Energy.
For sites where no gas is being consumed, including sites where the supply has been disconnected but not abolished, network charges from ATCO in respect of any gas meter(s) will apply and will be passed on at cost in addition to the daily supply charge noted above. Please note that these charges are often significant and will vary from site to site.
Network charges comprise of fixed or variable charges levied by ATCO.
For a copy of our Gas Standard Form Contract, please click here.
OTHER FEES & CHARGES
Gas Account Service Fees | Prices including GST | Prices including GST |
---|---|---|
Until 31st august 2024 | From 1st September 2024 | |
Account Set Up Fee No charge for account set up, even if you’re switching or moving. |
$0.00 | $0.00 |
Account Administration Fee – Business Small Use Customer | $2.19 per day per MIRN | $0.00 per day per MIRN |
Account Administration Fee – Residential Customer | 6.65 cents per day | N/A |
Bill Fee – Via Post Covers printing and posting costs |
$8.00 per bill Free via email/ MyAccount |
$0.00 |
Bill Copy Fee – Via Post Covers printing and posting costs |
$8.00 per bill copy Free via email / MyAccount |
$0.00 |
Overdue Notice Fee – Via Post Covers printing and posting costs |
$8.00 per notice Free via email |
$0.00 |
Dishonour Fee Covers costs incurred when a cheque or direct debit payment is dishonoured |
$10.00 | $0.00 |
Late Payment Fee | $50.00 per statement | $50.00 per statement |
Interest on Overdue Accounts | 1.5% monthly, calculated daily | Westpac corporate overdraft rate plus 2% per annum (per T&C’s) |
Credit Card Surcharge Covers credit card payment costs incurred by Perth Energy |
0.7% for MasterCard or Visa payment, 2.75% for American Express payment | 0.7% for MasterCard or Visa payment, 2.75% for American Express payment |
Gas Services / Works Fees | Prices excluding GST Until 31st August 2024 |
Prices excluding GST From 1st September 2024 |
Please note that Gas Services/ Works are direct pass-through fees from the network operator, and are updated annually on 01 January. | ||
Special Meter Reading Pass-through fees from the network operator to perform a special read on a basic meter |
$18.83 | $18.83 |
Booked Meter Read Pass-through fees from the network operator to perform a special read on a basic meter at an agreed date and time. |
$66.77 | $90.33 |
Meter Retake and Test Pass-through fees from the network operator to remove and test a meter in a laboratory. This fee is refunded if the meter is found to be faulty |
$196.09 $291.65 (AL12 meter) |
$262.93 $479.74 (AL12 meter) |
Apply Meter Lock Pass-through fees from the network operator to attend and disconnect the gas supply by applying a meter lock |
$44.61 | $58.23 |
Remove Meter Lock Pass-through fees from the network operator to attend and remove a meter lock |
$17.48 | $31.67 |
Deregistration Request Pass-through fees from the network operator to initiate a permanent removal of the meter |
$116.79 | $145.22 |
Remove Regulator Pass-through fees from the network operator to attend and disconnect the gas supply by removing the regulator |
$100.03 | $116.05 |
Reinstall Regulator Pass-through fees from the network operator to attend and reinstall the regulator |
$133.23 | $164.28 |
Disconnect Service in Street Pass-through fees from the network operator if supply disconnection can only be completed by disconnecting the service pipe in the street |
$784.85 | $1256.69 |
Reconnect Service in Street Pass-through fees from the network operator to reconnect gas supply that was previously disconnected in the street |
$883.21 | $711.75 |
Works Cancellation Fee Pass-through fees from the network operator where a customer cancels a request for a new connection |
$162.93 | $260.00 |
Trenching Fee Pass-through fees from the network operator where trenching is required as part of works maintenance |
N/A | As quoted by ATCO |
If you require Gas services or works that are not listed in the table below, please contact us for a quote specific to your residential or business address.
AGL | Perth Energy reserves the right to update, change or replace the rates at any time by posting updates and/or changes to our website.